How Agile Docs Rolls Up Estimates

Agile Docs rolls up estimates to parent issues by summing up the estimates of child issues when there’s no estimate attached to the parent issue.

For example, if an Epic has no story point estimate but has 2 child stories each with a story point estimate of 5. Agile Docs would assign the Epic a story point total of 10.

If the Epic had a story point estimate of 8 attached to it, Agile Docs would ignore the child stories and assign the Epic a story point total 8.

When you want to roll up an estimate from child issues, indicate this by removing the estimate attached to the parent issue.